IMEA Board Meeting Aug 29, 2024 “Highlights”

Note: This posting is a copy/paste of an email report to the NEST Energy Committee, where the formatting characteristics of the original email change when copy/pasting from Microsoft Outlook using the WordPress editor.


Hello Energy,

Rushing a bit to finish this report on a holiday weekend, so I apologize for any errors in my haste. Your eyes and the slides will keep me honest.

Sharing my “highlights” from the Thursday August 29 IMEA Board Meeting:

  1. 3 more Member contract renewals
  2. Update on 150MW utility scale solar project
  3. Discussion of decommissioning fund for coal plants
  4. Legal report on Federal court matters:
    Sierra Club vs Prairie State, and
    New Federal EPA Final Rule on CO2 Emissions
  5. Some additional noteworthy items,
    includes Prairie State, Trimble, audited financials, and more

The link to a copy of this meeting’s presentation slides pdf is:
https://drive.google.com/file/d/19WtKl8PTE_sxe30CKXg2iFyKQVDiezfm/view

The link to the CLEAN historical collection of board meeting slides, agendas, minutes, resolutions, etc. is posted on the CLEAN Sources and Resource webpage:
https://cleanenergynaperville.org/sources-and-resources/

The link to IMEA’s board meetings webpage is:
https://imea.org/IMEA%20Board%20Meeting%20Schedule.asp

1.  3 more Member contract renewals (slides 67 – 69)

  • The IMEA board adopted resolutions #24-08-924 through #24-08-926 to formally accept and approve the new contracts of Caryle, Red Bud, and Riverton

[Note: 23 of 32 Members have now approved new contracts vial local ordinances, followed by formal acceptance and approval of the IMEA Board:

  • 10 were accepted and approved at the April 27 board meeting: Princeton, Casey, Marshall, Altamont, Bushnell, Flora, Greenup, Roodhouse, Rantoul, and Oglesby
  • 10 were accepted and approved at the June 27 board meeting: Breese, Rock Falls, Farmer City, Sullivan, Waterloo, Highland, Bethany, Chatham, Metropolis, and Freeburg]

2.  Update on 150MW utility scale solar project (slide 74)

  • IMEA received the vendor’s draft of a long, in-depth PPA proposal on July 22
  • IMEA is working through the details and meeting weekly with the vendor
  • IMEA expects to reach substantial agreement on outstanding issues and terms, so that it plans to seek formal board approval at the October 2024 board meeting
  • The board also went into closed session to discuss some of the outstanding issues

3.  Discussion of decommissioning fund for coal plants  (slides 33 – 37)

  • IMEA proposes a Decommissioning Fund where funds will be collected from Members from May 2025 until 2035
  • IMEA says that it is a prudent utility practice to start collecting funds now to prepared for the final plant retirement obligations of Prairie State and Trimble County
  • Prairie State:
    • Set to retire in 2045 due to Illinois CEJA
    • IMEA’s 15.17% share of $168 Million in estimated decommissioning costs is $25.5 M in 2045 dollars
  • Trimble County:
    • “Unit 1 is slated to retired in 2045 – Unit 2 is currently slated to retire in 2050” [See note below with comment on the 2050 date for Unit 2]
    • IMEA’s 12.12% share of $90 Million in estimated decommissioning costs is $10.9 M in 2050 dollars
  • IMEA will budget to collect $2.17M per year and assume a 3% rate of return on the proceeds that are held, which is $0.57 per MWh added to the IMEA rate
  • It’s expected to increase Members’ average residential customer bill by less than 50 cents a month)
  • The board directed IMEA to prepare plans and a resolution for formal approval at the October or December 2024 board meeting

[Note:

  • The 5 IMEA slides contain additional information, and we should expect further details at the October board meeting.
  • That 2050 retirement date for Trimble County Unit 2 (also listed in the December IMEA Sustainability Plan) is apparently inconsistent with the majority owners planned 2066 retirement date as reported by Louisville Public Media:
    LG&E and KU plan to burn coal for another four decades
    https://www.lpm.org/news/2022-01-12/lg-e-and-ku-plan-to-burn-coal-for-another-four-decades
    ]

4.  Legal report on Federal court matters (slide 46)

  • Sierra Club vs Prairie State
    • Court denied Prairie State’s motion to dismiss the lawsuit
    • Response form Prairie State is due by September 23, 2024
    • Prairie State legal team analyzing options and strategy for next steps
  • New Federal EPA Final Rule on CO2 Emissions
    • Many legal challenges have been filed, including motions to Stay the new rules
    • Prairie State and IMEA CEO submitted Impact Declarations
    • All Motions for Stay were denied
    • US Supreme Court is now considering applications for Stay

5.  Some additional noteworthy items

  • President and CEO reports (slide 9 -13)
    • 70% of IMEA members are now pledged and an underlined list of 8 bullet points enumerating how “IMEA will be here to serve the needs of its members” (slide 10)
    • A list of agency updates since June (the previous board meeting), including Sept Exec Board meeting to be cancelled, and both Energy Efficiency committee and Member Generation committee requested to meet at IMEA offices (slide 12)
  • Closed minutes of Nov 6-7, 2019, June 17, 2021 and Nov 9-10, 2022 were again approved to continue to be restricted from the public.  Apr 27, 2023 and Dec 6, 2023 were released. (slide 17)
  • Operations – PJM (slides 18 -21)
    • PJM capacity auction prices for 2025/2026 Delivery Year were 833% higher than the 2024/2025 price of $28.92/MW-day
    • Impact to IMEA should be minimal due to IMEA long-term reliable resources and hedging
  • Operations – MISO (slides 22 – 26)
    • MISO concerns on thermal retirements and projections of insufficient long-term capacity
  • Operations – Wind (slides 27 -29)
    • Wind scheduling challenges because wind output is hard to forecast due to unpredictable weather patterns
  • Trimble County (slide 31)
    • Stack replacement design to be completed and construction timeline finalized in Spring 2025
    • Project to be completed in 2027-2028
    • IMEA share of costs is $10-11 Million, most already projected by IMEA
  • Prairie State (slide 32)
    • Fall planned outage moved to Nov-Dec
    • No further action on carbon capture
    • Prairie State staff is finalizing the 2025 budget with a proposed 2% increase in operating budget primarily due to insurance costs
  • Marshal and Princeton solar projects expected to be completed by end of year and Oglesby in spring 2025 (slides 42-44 Solar Project Update)
  • FERC has accepted MISO’s sloped demand curve, and rules are expected to increase the value of capacity (slide 47: Legal Report)
  • IMEA filed a limited project on MISO Resource Accreditation Requirements reform.(slide 48: Legal Report)
    • IMEA Member Generation  diesel Units would be penalized the same as natural gas units for natural gas winter performance problems
  • Presentation of completion of IMEA’s FY 2024 clean audit (slides 50-66)
  • Resolution #24-08-928 was approved to provide Winnetka a waiver on IMEA’s 1-year replacement policy (slide 73)
    • Winnetka is planning “to replace Unit #4 with two or three new generating units (estimated to be approximately 2,450 kW each)”
    • Current 1 year policy is inadequate and will likely be reviewed and update, so a waiver at this time was recommended.

—–

There was also an IMEA Exec Board meeting held on the previous day Wed Aug 28. When there are Exec Board meetings on the day preceding the regular Board of Directors meeting, the Exec Board agenda typically only covers items that are also included in the regular Board agenda. Therefore, I don’t spend limited time on providing a duplicative report on the Exec Board meeting. The CLEAN historical collection of board meeting records does include agendas and minutes of these meetings.

And finally no surprise that once again here’s my encouragement to attend IMEA board meetings. Public power also needs informed and knowledgeable citizens too. Webinar means not having to devote a whole day commuting to and from Springfield.

  • The IMEA’s board meetings webpage lets us know to mark our calendars for the next scheduled full IMEA Board Meeting on Oct 24, 2024 at 10:00AM, preceded by an Exec Board Meeting on Oct 23, 2024 at 2:00PM.
  • The webinar registration info is posted within the IMEA meeting agenda document file, typically posted at the end of the preceding week.
  • Also IMEA has now begun to publicly post the board meeting packet too. For this past week’s meetings, it was apparently posted in the afternoon/evening on Mon before the Wed/Thu meetings.

Thanks.

Greg

IMEA Board Meeting June 27, 2024 Highlights

Note: This posting is a copy/paste of an email report to the NEST Energy Committee, where the formatting characteristics of the original email change when copy/pasting from Microsoft Outlook using the WordPress editor.


Hello Energy,

Sharing my “highlights” from the Thursday June 27 IMEA Board Meeting:

  1. Next 10 Member contract renewals
  2. 150MW utility scale solar project
  3. Compensation for Member generation
  4. Legal report on US EPA Final Rule on CO2 Emissions
  5. Prairie State CCS
  6. Some additional noteworthy items

The link to this meeting’s presentation slides pdf is:
https://drive.google.com/file/d/1AKbt_DLMrj_aQw0wMDvX-KSIbshwwO9Z/view

There are no recordings offered by IMEA of IMEA board meetings, unlike our Naperville city council and many other public bodies.  The meeting minutes will become available after approved at the next IMEA board meeting.

Slides, agendas, minutes, etc.  from this meeting and previous board meeting are posted in the CLEAN google drive.
https://drive.google.com/drive/folders/1jWacdmtQ4yPRzkbUAjKWz4RVuwDzUEDM

This meeting’s slides and agenda files begin with the file prefix 2024-06-27_

The above link to the CLEAN IMEA Board Meetings google drive is also posted in the CLEAN Sources and Resource webpage:
https://cleanenergynaperville.org/sources-and-resources

1. Next 10 Member contract renewals (slides 67 – 76)

  • The IMEA board adopted resolutions #24-06-913 through #24-06-922 to formally accept and approve the next 10 Members who have approved their new Power Sales Contracts via local ordinances:  Breese, Rock Falls, Farmer City, Sullivan, Waterloo, Highland, Bethany, Chatham, Metropolis, and Freeburg
  • During the President and CEO report (earlier in the meeting), it was reported that several more Members have plans to approve in their upcoming city council meetings
  • The first 10 Members accepted and approved at the previous April 27th board meeting were:  Princeton, Casey, Marshall, Altamont, Bushnell, Flora, Greenup, Roodhouse, Rantoul, and Oglesby

2. 150MW utility scale solar project (slides 81 – 97)

  • The board approved IMEA proceeding with negotiations towards a final power purchase agreement with the proposed developer of a 150MW utility scale solar project in the Ameren IL region
  • IMEA expects to bring the finalized PPA back to the board for approval at the Aug meeting.
  • IMEA signed a Non-Disclosure Agreement, so the project and developer were not publicly revealed
  • Expected Commercial Operation Date (COD) is Dec 31, 2026
  • IMEA originally planned 100MW, but apparently needed to take the entire project’s 150MW or lose the project to a data center that the developer said was willing to take the entire 150MW
  • Solar was chosen over wind because solar best fits the IMEA deficit need for capacity and energy during summer months
  • Slides 82 – 85 provide graphs on the IMEA generation deficit with this project. Note that the curves above the red zero line represent the deficits IMEA is filling, and the curves below the red zero line represent surplus.
  • Any excess generation is expected to be manageable between 2027 and 2030. 2030 is when the Lee-DeKalb Wind PPA ends
  • The expected capacity factor for this solar project is 23% – 25%. When using 25%, the expected annual output is 328,500 MWh

3. Compensation for Member generation (slides 37 – 46)

  • IMEA is reviewing a transition to higher compensation levels for Member generation
  • 19 of 32 IMEA Members have Member generation contracts with IMEA
  • Existing compensation may be insufficient to upkeep the facilities in the future
  • IMEA approach intends to balance Members’ ownership costs and value these resources provide to the overall IMEA portfolio
  • Considering gradually increasing the production component and gradually create a floor as in the new 2035 Capacity Purchase Agreement
  • IMEA staff will work with the IMEA Generation Committee and expect to bring final recommendations to the full board in October

4. Legal report on US EPA Final Rule on CO2 Emissions (slide 51)

  • Copy/pasting from the slide:
    • Federal EPA says that Carbon Capture and Storage/Sequestration (CCS) technology is considered Best System of Emissions Reduction (BSER)
      • Under the new rules, all baseload coal plants will need to dramatically cut carbon emissions or retire early
      • Coal plants planning on retiring by 2039 must be equipped with 40% natural gas co-firing capability by 2030
      • Existing baseload coal plants will need to reduce carbon emissions by 90% by January 1, 2032
  • Legal challenges have been filed by 27 state Attorney Generals and other groups
  • Both IMEA and Prairie State have submitted impact declarations

5. Prairie State CCS (slide 34)

  • Copy/pasting from the slide:
    • PSGC staff continues to work towards due diligence to explore all options on potential Carbon Capture opportunity
      • Given the recent EPA regulations, owners continue to evaluate options (due diligence)
      • No progress has been made
      • No commitment from PSGC or the owners

6. Some additional noteworthy items

  • Average cost for FY 2023/2024 increased 2.5% to $82.56/MWh, primarily due to transmission cost increases (slide 6: Member Sales Report)
  • 20 of 32 members have now executed new contract agreements, and several more have plans at their upcoming city council meetings (slide 9: President and CEO Report)
  • IMUA has submitted a pre-application to receive federal grant funding for the Emergency Equipment Share project. IMEA may be needed to approve cost share (slide 17: Legislative and Regulatory Report)
  • Summer Readiness PJM Comments: Concerned that new generation is not coming online fast enough to replace retiring resources (slide 19: Operations)
  • MISO OMS Survey, released on June 20, projects growing capacity deficits (slides 24 – 25: Operations)
  • Wind performance is decreasing (slides 26 – 27: Operations)
    [Note: It may be first time I have seen IMEA publicly reveal MWh for Green River and Lee Dekalb]
  • Trimble County stacks replacement project is currently in the front-end engineering phase. Detail scope and construction timeline will not be known until the fall. Construction to begin in spring 2025 (slide 33: Trimble County)
  • Prairie State tube leaks in both units 1 and 2 (slide 34: Prairie State)
  • IMEA received official notice from Winnetka regarding its plans to replace Unit 4. Winnetka has also requested a waiver of IMEA’s 1-year replacement policy (slide 35: Local Transmission & Generation)
  • Staff is making progress on the PPA with SolAmerica for Highland, Carmi and Metropolis, but major sticking points remain (slide 47: Solar Project Update)
  • Marshall and Princeton projects with Altofer are expected to be completed by end of year, while Oglesby is expected to be Spring 2025 (slide 48: Solar Project Update)
  • ComEd Formula Transmission Rate update was filed on April 24. The first year impact on IMEA is expected to be a temporary one-year decrease due to the 2022 roll up credit. IMEA’s PJM peak also decreased to 504 MW. (slides 61 – 63: Legal Report)
  • Resolution #24-02-896 was amended to correctly reflect the April 30, 2025 end date for the contract renewal period (slide 80: Resolution #24-02-896 to Correct Scrivener’s Error)

And finally, here’s my encouragement to you to attend IMEA board meetings. Webinar means not having to devote a whole day commuting to and from Springfield.

  • The next scheduled full IMEA Board Meeting is Aug 29, 2024 at 10:00AM, preceded by an Exec Board Meeting on Aug 28, 2024 at 2:00PM.
  • The webinar registration info is posted within the IMEA meeting agenda document file, typically posted at the end of the preceding week.
    https://www.imea.org/IMEA%20Board%20Meeting%20Schedule.asp

Thanks.

Greg


IMEA Board Meeting Apr 25, 2024 Highlights

Note: This posting is a copy/paste of an email report to the NEST Energy Committee, where the formatting characteristics of the original email change when copy/pasting from Microsoft Outlook using the WordPress editor.


Hello Energy,

Sharing my “highlights” from Thursday’s Apr 25 IMEA Board Meeting:

  1. Acceptance and approval of the first 10 Member contract renewals
  2. Exploring an ownership share in a transmission project with Ameren’s ATXI
  3. Utility scale solar project status
  4. Some additional noteworthy items

The link to the meeting’s presentation slides pdf is:
https://drive.google.com/file/d/10sxkaClNxAVF6pI2PDXjY4rMwrb6qHdD/view

There are no recordings offered by IMEA of IMEA board meetings, unlike our Naperville city council and many other public bodies.  The meeting minutes will become available after approved at the next IMEA board meeting scheduled for June 27.  

Slides, agendas, minutes, etc.  from this meeting and previous board meeting are posted in the CLEAN google drive.
https://drive.google.com/drive/folders/1jWacdmtQ4yPRzkbUAjKWz4RVuwDzUEDM

Thursday’s meeting slides and agenda files begin with the file prefix 2024-04-25_

The above link to the CLEAN IMEA Board Meetings google drive is also posted in the CLEAN Sources and Resource page:
https://cleanenergynaperville.org/sources-and-resources

1. Acceptance and approval of the first 10 Member contract renewals (slides 41 – 51)

  • The IMEA board adopted resolutions #24-04-0900 through #24-04-909 to formally accept the first 10 Members who approved their new Power Sales Contracts via local ordinances
  • These new contracts cover the contract period Oct 1, 2035 through May 31, 2055
  • The 10 Members are: Princeton, Casey, Marshall, Altamont, Bushnell, Flora, Greenup, Roodhouse, Rantoul, and Oglesby
  • 2 others Breeze and Rock Falls were received after the meeting agenda was published, so they will be formally accepted and approved at the June board meeting. 
  • IMEA reports that several more Members have plans to approve contract in their May-June city council meetings.

2. Exploring an ownership share in a transmission project with Ameren’s ATXI (slides 30 – 33)

  • IMEA described a potential transmission ownership opportunity with Ameren’s ATXI division for which the board voiced their agreement for IMEA to further review and research to explore the opportunity
  • The project is a Princeton/Peru 138KV connection
  • Ameren will be the primary developer, contract and operator, and IMEA would be a minority owner
  • Preliminary projections of $20-$30 million might be funded from IMEA liquidity or an IMEA bond issue
  • IMEA’s capital investment in the project would be recovered through the MISO transmission funding process
  • IMEA staff will evaluate and report back to the board

3. Utility scale solar project status (slide 36)

  • The Sustainability Plan seeks 100MW solar by end of 2026
  • The IMEA CEO reports that utility scale solar prices are 75% higher than 5 years ago (in 2019 when IMEA finalized solar contract with Ranger Power’s Big River project)
  • Staff discussions and due diligence currently continues with one vendor
  • If discussions with the vendor continue to be fruitful, IMEA anticipates a term sheet by June followed by formal contract approval in August

4. Some additional noteworthy items

  • President and CEO report (slides 10-18)

IMEA expects to be able to refinance $400M of the outstanding 2015A bonds with a potentials savings of $30 million. The refi but will not extend the length beyond current 2035, Authorization will be sought in late 2024 or early 2035 (slide 13)

  • Operations: PJM (slide 20)

Base Residual Auction (BRA) results for 2024/2025 stand after appeal to US Court of Appeals, so no change to IMEA’s PJM capacity costs for planning year 2024/2025

  • Trimble County report (slide 27)

Detail scope and timeline expected late summer 2024 for the project to build new powerplant stacks for both units 1 and 2

  • Prairie State report (slide 28)

No change in Prairie State CCS status: “No updates since last reported” and “No commitment from PSGC or the owners”

  • Behind the Meter solar projects (slides 34-35)
  • Legal report (slides 37-40)

Latest numbers on Winter Storm Elliott’s impact: Penalty [for Trimble County] $2.264 Million, Performance Payment $4.578 Million, Net $2.214 Million

  • Meeting schedule for FY24-25 (slide 57)
  • Committee assignments for FY24-25 (slide 58)

And as usual at the end my board meeting emails, here’s my encouragement again to you to also attend IMEA board meetings. Webinar means not having to devote a whole day commuting to and from Springfield.

The webinar registration info is posted within the IMEA meeting agenda documents, typically posted at the end of the preceding week.

https://www.imea.org/IMEA%20Board%20Meeting%20Schedule.asp

Next scheduled full IMEA Board Meeting is June 27, 2024 at 10:00AM, preceded by an Exec Board Meeting at 2:00PM June 26, 2024.

Thanks.

Greg


IMEA Board Meeting Feb 15, 2024 Highlights

Note: This posting is a copy/paste of an email report to the NEST Energy Committee, where the formatting characteristics of the original email change when copy/pasting from Microsoft Outlook using the WordPress editor.


Hello Energy,

Sharing my selection of “highlights” from Thursday’s Feb 15 IMEA Board Meeting:

  1. Approval of the forms of the new contracts
  2. IMEA’s verbal presentation on the muni-coop transparency legislation
  3. IMEA goals for fiscal year 2025
  4. Presentation and approval of both the revised FY 2024 budget and the new FY 2025 budget
  5. Nominations and approval of the Executive Board for FY 2025

Followed by:

  • Text of comments on the new contract by our Naperville Electric Director at the previous day’s IMEA Executive Board Meeting (He was unable to attend the Thur board meeting due to his required attendance at a union arbitration hearing that could not be rescheduled), and
  • an appendix with my notes on additional board meeting slides

The link to the meeting’s presentation slides pdf is:

https://drive.google.com/file/d/1jJCaW2N39vjC-_jQ0nebKSlefEwowKRe/view

Slides, agendas, minutes, etc.  from this meeting and previous board meeting are posted in the CLEAN google drive.

https://drive.google.com/drive/folders/1jWacdmtQ4yPRzkbUAjKWz4RVuwDzUEDM

Thursday’s meeting slides and agenda files begin with the file prefix 2024-02-15_

The above link to the CLEAN IMEA Board Meetings google drive is also posted in the CLEAN Sources and Resource page:

https://cleanenergynaperville.org/sources-and-resources/

IMEA provides us no recordings of the meetings, unlike our Naperville city council and many other public bodies.  The minutes will become available once approved at the next IMEA board meeting scheduled for April 27.  If there’s interest, I would be willing to host a Q&A zoom to review and discuss this Feb 15 meeting.

1. Approval of the forms of the new contracts  (slides 41 – 44)

  • Forms of the new contracts were unanimously approved by the 22 Member representatives in attendance.
  • A package will be sent out by end of month to all the Members with a cover letter, new contract forms, and draft language for Members to consider using in their municipal resolutions/ordinances approving the contracts. [We learned at December’s board meeting that the time period to consider renewal is up to 14 months, Mar 1, 2024 to Apr 30, 2025]
  • As I described earlier, our Naperville Electric gave comments at the previous day’s Executive Board meeting. Thetext of his comments are below, following item 5 in this  email.
  • Slide 41 lists several changes to the new power sales contract form, since the December board meeting.

One change is a clarification that IMEA-sponsored projects in Member municipalities do not count against the Member Directed Resources (MDR) limit. Such IMEA-sponsored projects include the IMEA 1 MW solar project in Naperville at Springbrook and possible future IMEA-sponsored battery storage projects within a Member’s municipality

  • Slide 42 lists several changes to the Capacity Purchase Agreement. These agreements apply only to those Members who dedicate their local generation resources to IMEA. Winnetka’s natural gas generation is an example.

The 2015 IMEA bond prospectus contains this description on pdf file page 37, footer page number 25:

IMEA’s Participating Members with existing fossil fuel-fired generating units have dedicated such facilities to IMEA under Capacity Purchase Agreements (“Dedicated Capacity”). Approximately 295 MW net tested capability of Dedicated Capacity is available to IMEA upon request to meet its load requirements. Due to the age and relatively higher costs of fuel utilized, these facilities are generally best suited for use as peaking and reserve capacity. Table 5 below summarizes the existing dedicated generating resources of the Participating Members.

https://drive.google.com/drive/folders/1m48LekH86aZ6DR9NiwEajOl5pIqjt__z

2. IMEA’s verbal presentation on the muni-coop transparency legislation (slide 16, from the legislative & regulatory report section of the meeting)

  • Slide 16 lists “Transparency Legislation” as a bullet point. Further details were provided verbally by the IMEA Legislative Director. 

Sharing items from my notes on what was said by the Legislative Director  [and offering my comments after]:

HB5021 and corresponding language in SB3637 has a dramatic impact on munis, agencies, and coops

  • “chock-full” of new requirements
  • imposes an Integrated Resource Planning (IRP) requirement
  • imposes a renewable portfolio standard (RPS)
  • puts in state oversight and cedes local control for the first time in history
  • your power supply and policies have always been city council regulated
  • IMEA already has a higher renewable percentage than the state
  • IMEA already has a sustainability plan commitment
  • we don’t think resource decisions should be made by the state
  • whole host of transparency requirements
  • already on IMEA website or in IMEA board meetings
  • budgets, resources, capital expenditures, others
  • prime example is budget in today’s meeting
  • munis are the most transparent in the state
  • with OMA, FOIA, and our board meetings, don’t think that can be disputed
  • net metering was already negotiated in CEJA
  • some eminent domain provisions may cause muni problems with the way they are written

[

COMMENTS:

First, please I encourage you to become well-versed on the transparency issues. Meeting the letter of the law with respect to the Open Meetings Act (OMA) and Freedom of Information Act (FOIA) are ground level requirements, but alone are not sufficient to provide transparency in many key areas. Descriptions, explanations, and examples are provided in our CLEAN “Lack of Transparency” webpage and detailed document:

https://cleanenergynaperville.org/did-you-know/lack-of-transparency/

Second, from my perspective regarding transparency on matters in our local Naperville electric utility, Naperville does a pretty good job on that transparency. I also appreciate our Electric Director’s time, efforts and genuine interest in dialogue and providing transparency. But when we cross over into power supply and IMEA matters, transparency apparently depends on what IMEA will provide.

Let’s take a look at that “prime example” noted above from the words of IMEA: the IMEA budget. 

  • IMEA budget presentations and the votes to approve the budget occur in the very same IMEA board meeting, even though this is a $350 million annual budget with a corresponding balance sheet of $1.2 billion in assets. Compare that with the City of Naperville budget process, which is publicly posted and reviewed by city council in workshop meetings over a period of months. Not suggesting that there shouldn’t be meaningful differences between the two, but that same day IMEA presentation and vote is quite striking.
  • In advance of the board meeting, the IMEA board members receive a copy of the proposed budget and budget resolution documents. Apparently no one else sees a copy.  Those budget resolution documents, as well as all other IMEA resolution documents, are not posted online and not available to the public in advance of the board meetings.
  • The citizens and ratepayers who are financially responsible for paying those IMEA monthly bills have no advance opportunity to review, question, and offer stakeholder input.  Compare that with Naperville budget workshops and city council meetings where resolutions, ordinances, and supporting materials for agenda items are posted online in advance of the meetings. They are available for public review, questions, comments, and even time to contact council members and city staff.
  • Contrary to the IMEA claim, this “prime example” would appear to suggest that this budget of IMEA is quite a bit low on the scale that measures transparency.

]

3. IMEA goals for fiscal year 2025 (Slide 14, part of President and CEO’s report)

  • Note that IMEA FY2025, also referred to as FY24/25, runs from May 1, 2024 to April 30, 2025
  • Here are the goals copy/pasted from  slide 14. [Note the contract renewal goal of at least 20 members.]
  • Complete FY 24/25 below approved budget
  • Maintain Debt Service Coverage of 1.20 at fiscal year end
  • Visit each Member at least once in fiscal year
  • City Council meetings/workshops to provide IMEA/IMUA background
  • Maintain all current financial ratings agency status
  • Complete Ameren WCA/UCA agreements and host Member workshops for those affected by the outcomes
  • Execute at least 20 new IMEA Power Sales Contract and have them approved by IMEA Board by April  30, 2025
  • Complete installation of 3 current BTM solar projects by April 30, 2025
  • Negotiate contract(s) for 100MW of utility grade solar and have IMEA Board approve by April 2025  Board meeting
  • Extend IMEA Demand Response Program for FY 24/25 and sign up at least 4 retail customers
  • Evaluate Ameren WDS rate change proposal and determine IMEA’s efforts to mitigate increases
  • Evaluate and provide recommendations to Board for next 3-year Energy Efficiency & EV Programs
  • Complete study of installing utility scale, BTM battery storage unit within a member system to be completed by December 31, 2025
  • Determine options and most cost-effective method(s) for a Conservation Voltage Reduction Program by December 31, 2025

4. Presentation and approval of both the FY 2025 budget and the revised FY 2024 budget (Slides 45 -59)

  • Copies of the two budget resolutions have been requested from IMEA. I expect to receive them next week after they are formally signed.

When received, the resolutions will be uploaded into the publicly shared CLEAN  IMEA Board Resolutions directory:

https://drive.google.com/drive/folders/1Z3rPQTGKKmqN9IzjFaFormy0UUQuhJPd

  • Slide 45 provides a graph of IMEA Rates 2015 to 2024 titled “IMEA Actual Rates Consistently Under Budget”
  • Resolution/ordinance 24-02-897 and slides 46-52 contain the revised budget for the current fiscal year 2024 which ends Apr 30, 2024

My notes:

Operating expenses lower than original estimates

Purchased power costs are lower

  • IMEA is selling power in PJM [Prairie State and Trimble County are located in MISO and both are pseudo-tied to PJM]

Prairie State and Trimble County fuel costs increased

Trimble County O&M increased while Prairie State decreased

Transmission costs are lower than original estimates

  • Ameren charges lower due to lower peaks [network service charges are based on peak]

IMEA’s A&G expenses are lower

  • Compared to peers, lowest of any Joint Action Agency

No board member questions or discussion prior to approval

  • Resolution/ordinance 24-02-897 and slides 52-59 contain the budget for fiscal year 2025 that begins May 1, 2024

My notes:

Planned Prairie State Outages

  • PS1-10 day fall outage
  • PS2-28 day fall outage

Planned Trimble County Outages

  • TC1-9-day fall outage and 16-day spring outage
  • TC2-65-day fall outage (turbine) and 16-day spring outage

Capital budget higher than FY24 Revised Budget

– TC capital requirements for stack projects engineering and prep [Earlier TC report during the meeting reported stacks for both units]

Purchase power costs to increase

  • Due to lower generation from planned outages + less favorable market than FY2024 [less market sales to offset purchases]

Lowr fuel costs due to planned outages at Prairie State and Trimble

Transmission costs increase [Ameren and ComEd network service charges]

Budgeting for three new staff members: PSC Supervisor, Project Manager (if needed) and Government Relations staff person

No board member questions or discussion prior to approval [My memory of the day before Exec Board meeting tells me that there was one question about the Project Manager position. It’s budgeted, but will not be filled without coming back to the board for approval]

5. Nominations and approval of the Executive Board for FY 2025 (Slide 62)

  • Our Naperville Electric Director, Brian Groth, was nominated and approved by the Members to serve as Vice-Chair of the full IMEA Board for FY2025 which starts on May 1, 2024.
  • Copy/paste from slide 62 of the nominations and approvals. All nominations were unanimously approved.
  • Cory Sheehy, Marshall as Chairman
  • Brian Groth, Naperville as Vice Chairman
  • Dan Cook as Secretary/Treasurer
  • Troy Fodor as Assistant Secretary/Treasurer
  • David Coston, Carmi
  • Pat McCarthy, Chatham
  • Sue McLaughlin, Farmer City
  • John Tolan, Freeburg
  • Pete Suhr, St. Charles
  • Mike Kirk, Sullivan

Text of Naperville Electric Director’s Comments at the Feb 14 IMEA Executive Board Meeting.  (The text was emailed to me along with permission to share.)

Let me first start by noting that I will not be at the full board meeting tomorrow as we have a union arbitration hearing in Naperville for which I need to be in attendance. This hearing was scheduled over six months ago and could not be rescheduled.  

From time-to-time local commitments cause conflicts and I wanted to be transparent on the reason for my absence tomorrow. Thank you for the understanding.

With respect to the resolution authorizing the president and CEO to seek contract extensions from current IMEA members, I believe the following comments are a fair and accurate summary of both the agency’s work on this topic as well as Naperville’s efforts to date. 

By voting for the approval of the standard form of the contract and authorizing the president and CEO to seek contract renewals this board is not binding any member’s community to a contract extension, this is simply starting the conversation of who will remain in the agency at 2035 so that the agency can begin planning how it will support those members beyond this date.

While the contract may be one document that governs the interaction between the municipalities and the agency, I would not like to lose sight of the sustainability plan, which is a living breathing document which was approved by the board and outlines the agency’s sustainability goals as well as the process by which agency staff will regularly update the board, and member municipalities, on these goals. We also should remember our work here as the Board of Directors. All of this comes together to provide affordable, sustainable and reliable power to all of our customers.

From a local perspective, Naperville continues to review the proposed contract documents with internal and external legal counsel as well researching all options available to the City through its work with consultants. To that point, we have and will continue to seek stakeholder input on contract terms and language, proposing additions and/or changes as warranted.

I appreciate all of the work agency staff have put into this contract proposal,  listening to members of the contract working group to incorporate key changes to the document, I was a part of this working group and experienced first hand the level of effort that went into this document.  Through my participation in the working group, I understand the agency and boards desire for a single contract form between all members and also understand that each community may seek to have a different energy mix today and in the future.  I am confident that at the end of the day our collective work will give all members the flexibility to utilize local control over their energy mix while ensuring that all members are protected from the cost shift that could occur with increased utilization of the Member Directed Resources concept. 

Our work on this contract extension continues with the common goal of providing reliable energy delivery to our communities now and in the future.

Appendix of My Further Meeting Notes

  • Behind the Meter (BTM) and Utility Scale Solar (Slides 26 – 29)

Looks like Altofer is likely to be selected for the contract to develop BTM projects in Marshall, Oglesby, and Princeton

SolAmerica works continues for USDA PACE loans for projects in Rantoul, Highland, Carmi, and Metropolis

IMEA reports that they are in steady contact with 4-5 utility scale solar projects

Projects continue to experience delays: mineral rights/land title, interconnection, supply chain

Developers want to push risks back on IMEA

IMEA is also in competition with large corporations such as Amazon with their own clean energy goals

Costs are nearly double what they were back in 2019

  • Operations – MISO (Slide 19)

Warnings on future capacity deficits in MISO

Gap of 9 GW in MISO planning year 28-29

  • Operations (Slide 20)

Three IMEA Members hit all time peaks in January

  • Trimble County (Slide 21)

Sounds like large expenditures are coming to rebuild stacks for both units TC1 and TC2

  • Prairie State (Slide 22)

No reported change in carbon capture project status

  • How Do PJM Capacity Market Changes Impact IMEA (Slides 33-34 of the legal report)

FERC approved filing ER24-99 for PJM to again change the way it determines capacity for the capacity markets

IMEA is “well hedged” with ownership of thermal resources (coal-fired units) for the expected impacts of reduced capacity credit and increasing capacity prices

  • Resolution 24-02-899 Revised Schedule A for Naperville (Slide 40)

The board approved changes to Naperville’s IMEA Schedule A

Resulting from the shutdown on Dec 31 of two co-generation units at the former Amoco site.

Schedule A identifies the measurement points of energy “delivered by IMEA”. 

[My understanding is that these are the IMEA/PJM metered locations where the high voltage PJM/ComEd transmission network meets the Naperville local distribution network.]

  • Financial Projections and IMEA Member Rates (Slides 60-61)

The main message is: our IMEA costs and your Member rates remain stable, except for increasing transmission costs from ComEd and Ameren

—–

As usual at the end my board meeting emails, here’s  my encouragement to you to also attend IMEA board meetings. Webinar means not having to devote a whole day commuting to and from Springfield. Ted, from Energy Committee, attended for the first time, and Maureen was again able to squeeze in part of the meeting with her work schedule.

The webinar registration info is posted within the meeting agendas, typically posted at the end of the preceding week.

https://www.imea.org/IMEA%20Board%20Meeting%20Schedule.asp

Next scheduled meeting is the IMEA Executive Board meeting on Mar 27, 2024 at 10:00AM

Next scheduled full IMEA Board Meeting is April 25, 2024 at 10:00AM, preceded by an Exec Board Meeting at 2:00PM the day before April 24, 2024.

Thank you.

Greg


IMEA Board Meeting Dec 7, 2023 Highlights

Note: This posting is a copy/paste of an email report to the NEST Energy Committee, where the formatting characteristics of the original email change when copy/pasting from Microsoft Outlook using the WordPress editor.

A copy of email attachment file 2023-12-07_IMEA_BOD_Slides_NewContract.pdf is available here. It has the 10 new contract slides extracted from the full set of board meeting slides.


Hello Energy,

Sharing my selection of “highlights” from today’s IMEA Board Meeting …

Slides, agendas, minutes, etc.  from this meeting and previous board meeting are posted in the CLEAN google drive.

https://drive.google.com/drive/folders/1jWacdmtQ4yPRzkbUAjKWz4RVuwDzUEDM

Today’s meeting slides and agenda files begin with the file prefix 2023-12-07_

The above link to the google drive is also posted in the CLEAN Sources and Resource page:

https://cleanenergynaperville.org/sources-and-resources/

Note also that there was a closed IMEA Special Board Meeting yesterday December 6 for which we have no information other than the agenda.

Sharing only 3 main items from today’s Dec 7 meeting and leaving the rest of the slides to you.  

  • starting first with the proposed new contract which I believe is of interest to most of us,
  • then the sustainability plan vote, and
  • end with Prairie State

Happy to answer questions about the meeting or any other questions during the open Naperville/IMEA & Power Supply Q&A this Tuesday Dec 12 6:45pm to 7:15pm. It will end 15 minutes before the start of the NEST Energy Committee meeting. Old guys like me need the break.

Proposed New Contract (slides 51 – 60 and which are also extracted from the full set of slides and attached as a pdf to this email)

[COMMENTS: I encourage you to closely review all 10 of these slides and they are attached.]

Slide 51 (page 1 in the attached extract)

  • Our Electric Director Brian Groth actively participated in the new contract working group

Slide 59 (page 9 in the attached extract)

  • Forms of documents will be approved at the February 2024 IMEA board meeting
  • Members will have a time frame of 14 months (March 1, 2024 – April 30, 2025) to approve

Side 54 (page 4 in the attached extract)

  • Contract Length – October 1, 2035 to May 31, 2055

Slide 55 – 58   (pages 5 – 8 in the attached extract)

  • Member Directed Resources (MDR)

If Members desire an added portion of self-controlled, locally developed sources as a portion of Member power supply needs

  • Provision in contract allows the Member to seek and gain approval for self-directed carbon-free resources
    • Wind, Solar, Biomass, Nuclear, Other carbon- free source that meets IL CEJA laws
    • Clean Energy production rules
  • For up to 10% of Member Peak Load
  • Member can place MDR within their distribution system or inside the current transmission system they are already served by ComEd or Ameren-Illinois
  • Member can begin the MDR process once the new contract is signed. Does not have to wait until 2035

Slide 60  (page 10 in the attached extract)

  • Why now …
  • Need to plan now
  • Needs are now for 100MW of [utility scale] solar
  • IMEA resource agreements nearing expiration
    • 70MW Lee Dekalb Wind (2030)
    • 50MW Green River Wind (2035)
    • 25MW Big Rivers Solar (2035)
    • 45% of Prairie State output (2035/2038)
  • Long-term deals are priced lower
  • Longer wait will impact costs/options
  • Impossible to plan without knowing how much power

[COMMENTS:

  • The new contract would lock us into further long-term commitment to those coal-fired generation resources at Prairie State and Trimble County
  • We need to understand from our Electric Director if/how MDR might work for us.
  • MDR does not appear to allow a contract with another power supply vendor for that 10%; only allows us to deploy our own resources and for which we would be able to take advantage of financial incentives such as direct pay of tax credits

]

Resolution and Vote to Approve IMEA Sustainability Plan (slides 38 – 50)

  • Resolution to approve was unanimous
  • I received confirmation on the vote results from our Electric Director, as there was a webinar malfunction during the voting such that remote attendees could not see or hear the vote results
  • Prior to the vote, our Electric Director:
  • Thanked the Agency and working group for setting a vision and policy to formally begin the transition to net zero by 2050
  • Said there’s lots of work still to be done; It’s a living , breathing document; and Naperville will continue to bring ideas

[COMMENTS:

  • We expressed our comments at city council on Tuesday evening Dec 5.
  • If you did not watch the city council public comments and then council discussion at the very end of the meeting, I encourage you to do so.
  • Full council recording is here:

https://naperville.granicus.com/player/clip/1603

Video clips are available on YouTube:

Public comments

https://youtu.be/Uuqjj7FdLtY

Council discussion

https://youtu.be/XmO4w1_P3nk

]

Prairie State Report (slides 26 and 27)

Slide 26

  • Documents that long-term operational and decommission planning has begun
  • Actual decommissioning process would being in 2046

Slide 27

  • Prairie State Carbon Capture status appears to be unchanged, sine last meeting
  • On-going discussions with a consortium of companies that have interest in building a carbon capture system
  • Consortium involves companies with a focus on 1) project development, construction, and operations, 2) project financing, 3) CO2 transportation, and 4) underground storage of CO2
  • Working towards development of a Memorandum of Understanding (MOU) with the basic framework of a potential definitive transaction → Continue to seek satisfactory terms for PSGC owners
  • Still no PSGC commitment to proceed
  • The University of Illinois (U of I) submitted an application for a $350M grant from the DOE in May
  • No update from DOE on the grant

Always have to end my board meeting emails with my encouragement to you to attend IMEA board meetings. You no longer have to devote a day trip to Springfield to attend. Webinar registration info is posted within the meeting agendas posted at:

https://www.imea.org/IMEA%20Board%20Meeting%20Schedule.asp

Next scheduled meeting is the IMEA Executive Board meeting on Jan 17, 2024 at 10:00AM

Next scheduled full IMEA Board Meeting is Feb 15, 2024 at 10:00AM.

Thanks.

Greg


City Council and Mayoral Candidate Election Resources

The April 4 city council and mayoral elections will play a significant role in our Naperville clean energy future.

Here are some candidate forum recordings and other resources to help you in your voting choices for the next Mayor of Naperville and the 4 of 8 seats on city council.


Naperville Environment and Sustainability Task Force (NEST)

Candidate Forums and Questionnaires Webpage

City Council Candidate Forum – March 8, 2023

City Council and Mayoral Candidate Environmental Questionnaire Responses


League of Women Voters of Naperville

Voter Resources

Naperville City Council Candidate Forum – February 20, 2023

Naperville Mayor Candidate Forum – February 23, 2023


Naperville Area Homeowners Confederation (NAHC) and Senior Task Force

City Council Candidate Forum – January 31, 2023


Naperville Community Television (NCTV17)

Naperville Election 2023 Candidates


12 City Council and 2 Mayoral Candidates File

The Naperville Sun and Daily Herald report that 12 candidates for Naperville city council and 2 candidates for Naperville mayor filed their paperwork at the city clerk’s office Monday morning for the April 4 election.

The candidates for Naperville mayor are:

  • Benny White
  • Scott Wehrli

The 12 candidates for 4 seats on Naperville city council are:

  • Patrick Kelly (incumbent)
  • Meghna Bansal
  • Nag Jaiswal
  • Allison Longenbaugh
  • Rebecca Malotke-Meslin
  • Josh McBroom
  • Derek McDaniel
  • Ashley South
  • Ashfaq Syed
  • Jodi Trendler
  • Madhu Uppal
  • Nate Wilson

Please join us in advocating that these candidates support a clean energy transition off of our coal-fired ownership.

Links to the Naperville Sun and Daily Herald articles: